top of page
Cincinnati Music Hall_Central Parkway_Crop.jpg

THE PROCESS

DOTE has developed a plan to improve the north-south section of Central Parkway between Plum and Liberty streets. The project is following ODOT’s five-phase Project Development Process:

  • Planning Phase

  • Preliminary Engineering

  • Environmental Engineering

  • Final Engineering and right-of-way acquisition (if necessary)

  • Construction

The Project is currently in the Environmental Engineering Phase of the plan.

 

The Preliminary Engineering Phase, initiated in 2023, included an online survey, in-person public open houses, and virtual sharing of materials for the public to contribute their input on the project.

​

THE PREFERRED ALTERNATIVE PLAN

A Preferred Alternative was presented at a public meeting in October of 2023. Following a public comment period, the City finalized the Preliminary Design Report. The final alternative presented in the final preliminary design report underwent minor modifications following the public meeting. 

​

View the Final Report here.

View the October Public Meeting Comments here.

View the Central Parkway Renderings here.

Central Parkway_Plan View.jpg
Central Parkway S1004344_1200.jpg

​

DOTE is currently advancing this project in a phased approach, beginning with the detailed design of the improvements from Ezzard Charles Drive to Liberty Street (Phase 1). The Environmental Engineering Phase began in the Summer of 2024 with detailed engineering analysis and design. A view of the illustrative plan, based on the current level of design for the first phase can be found here.

Central Parkway Crosswalk Left-627713360.jpg

SCHEDULE

Below is the project's tentative schedule:

Preliminary design, cost estimates, and public engagement

9 months

Central Parkway Timeline 052523_3.jpg

SPRING
2023

WINTER
2024

CONTINGENT UPON FUNDING

Construction

16 months

 Final design and engineering

12 months

During construction, DOTE expects the traffic impact for motorists to be minimal. DOTE construction management staff will always be on site during construction and will coordinate construction activity with all bordering property owners, businesses and operators, and residents as needed.

Central Parkway Crosswalk Right-627713360.jpg

CONSTRUCTION TIMING

The bulk of project planning and related work (such as detailed engineering, property acquisition and utility relocations) cannot be completed until a Preferred Alternative has been identified. Following identification of the preferred alternative, the bulk of construction will be performed shortly after designs are finalized and will be completed over the course of a 16-month period.

bottom of page